Libya’s Sharara oil field has lost about 350,000 barrels a day of output after an “outlaw group” shut a valve on its pipeline, the National Oil Corporation (NOC) said on Monday.
It is the second blockade of the country’s crude network in less than a month.
Sharara is Libya’s largest field and the loss amounts to more than a quarter of the 1.19mn barrels a day the country exported in October. At Monday’s Brent price of about $92 a barrel, 350,000 barrels a day is worth roughly $32mn a day, by DNE Africa’s calculation.
What did the NOC say about the Sharara oil field?
The National Oil Corporation said in a statement on its Facebook page that the closure of a valve on the Sharara oil field pipeline by “an outlaw group” was causing the loss of about 350,000 barrels a day. The statement was reported by Asharq Business (in Arabic) early on Monday.
The corporation called on the Petroleum Facilities Guard and the relevant government bodies to protect oil installations, prevent any interference with their work and step up efforts to reopen “the two lines” and restart production. It said it would take all legal measures to pursue those responsible. The NOC did not name the group or say when output might resume.
What about the Hamada pipeline?
The Sharara oil field shutdown came two days after the NOC said an armed group had kept the Hamada pipeline closed for more than 20 days. That blockade had cost about $30.8mn up to 21 November through the loss of 302,800 barrels of crude, the NOC said, an average of about 15,000 barrels a day, or roughly $1.47mn of revenue a day, plus the fixed operating costs of the affected fields.
The Hamada loss is small next to Sharara’s. Together the two closures leave Libya’s western crude network, which feeds the Zawiya refinery and export terminal near Tripoli, exposed to armed groups that use blockades to press their demands.

Has the Sharara oil field been shut before?
Yes, often. In September an armed group closed the pipeline that carries Sharara oil field crude to the Zawiya port, cutting output and threatening exports and the refinery, as DNE Africa reported at the time. The NOC said then that the closure had cost more than 720,000 barrels and over $75mn by 24 September. Production recovered to about 340,000 barrels a day by the end of that month, according to Bloomberg.
The field sits in the Murzuq basin in Libya’s south-west and is operated by Akakus Oil, a joint venture between the NOC and foreign partners led by Spain’s Repsol. The NOC declared force majeure at Sharara in January 2024 during an earlier closure.
What does it mean for Libya’s oil revenue?
Oil provides almost all of Libya’s export earnings and state revenue. Crude exports fell in October to 1.19mn barrels a day, the lowest since June, according to Bloomberg data reported by Asharq Business. The NOC wants to raise production to 2mn barrels a day by the early 2030s.
NOC chairman Masoud Suleman estimated in August that the sector needs $30bn to $40bn of investment, and said more than 60 discovered oil and gas fields had not been developed for lack of funding. Repeated closures of the Sharara oil field undercut that pitch to investors.
The blockade also comes as Libya’s divided authorities face pressure over foreign military activity, after Ukraine said its drones sank a Russian corvette at Benghazi on Sunday. The next test is whether the Petroleum Facilities Guard can reopen the valve, and whether the NOC declares force majeure on Sharara crude loadings.
FAQ
Why has the Sharara oil field output fallen?
The NOC said an “outlaw group” closed a valve on the field’s pipeline, causing the loss of about 350,000 barrels a day.
How big is the Sharara oil field?
It is Libya’s largest oil field, producing about 340,000 to 350,000 barrels a day when running normally.
What is the Hamada pipeline closure?
An armed group has kept the Hamada pipeline shut for more than 20 days, costing about $30.8mn up to 21 November, the NOC said.
Has Libya declared force majeure?
Not on this closure by the time of publication. The NOC declared force majeure at Sharara in January 2024.