Uganda has paid Shs373.07bn (about $100mn) to 7,721 of the 12,946 people affected by the Malaba-Kampala railway, Works and Transport minister Fred Byamukama told Parliament on 17 November.
The payments give the state 2,108 of the 3,536 acres needed for the 272km standard gauge line, which is meant to link Uganda to Kenya’s network and the port of Mombasa. A further Shs472.45bn is still owed to the remaining households, the minister said, according to a statement from the Parliament of Uganda.
How far has land acquisition for the Malaba-Kampala railway gone?
Byamukama said acquisition was most advanced between Malaba, on the Kenyan border, and Mayuge, where about 98 per cent of a continuous corridor had been secured. “We now have adequate corridor of approximately 130km where the contractor can start works,” he said, adding that compensation would continue with priority given to sections critical for construction.
He did not say when the outstanding Shs472.45bn would be paid. That sum is larger than the amount already disbursed, which means more than half of the compensation bill for the Malaba-Kampala railway is still to come.
What has the contractor done so far?
For the Malaba-Kampala railway, the government issued a Limited Notice to Proceed to Yapi Merkezi, the Turkish contractor, while financing for the full works is finalised. Byamukama said the preparatory contract, valued at €75mn (Shs341.63bn), ran from 14 May 2025 to October 2026 and covered surveys, geotechnical investigations and the purchase of earth-moving and other equipment.
“The LNTP remains a preparatory arrangement pending financial close and issuance of the full Notice to Proceed,” the minister said. In other words, full construction cannot begin until the funding package is closed.
How is the project being financed?
Uganda has been assembling loans for the Malaba-Kampala railway, a project put at about €2.7bn. In April it appointed Citibank to mobilise the financing, Engineering News reported, and the Islamic Development Bank has approved a loan for the line, according to New Vision. Export credit agencies in Turkey and Poland have also been named as possible lenders. Uganda awarded the construction contract to Yapi Merkezi in 2024 after cancelling an earlier arrangement with a Chinese firm.
The eastern route is the first phase of Uganda’s wider standard gauge plan. Its value depends on Kenya extending its own line from Naivasha to the Malaba border, which has stalled for lack of funding, The EastAfrican reported. Tanzania, meanwhile, is pressing ahead with its own railway towards the region, as we reported on its $2.4bn line to Burundi and Congo.
What did MPs raise?
Asinansi Nyakato, the shadow minister for works and transport, said delays in compensating affected people had pushed up the cost of the Malaba-Kampala railway. She also asked how much had been set aside for climate risks, citing an earlier resolution of Parliament that transport budgets should cover them.
Byamukama said Shs11bn had been earmarked in the project budget for environmental safeguards and would be raised if needed.
Abdul Bisaso, MP for Kassanda County South, said residents with land titles near the corridor feared displacement after Uganda Railways Corporation staff marked their houses for demolition without notice. The minister said the demolitions in Kassanda had affected property found to be inside the gazetted railway reserve. “We shall do boundary opening where the corridor is contested with the public,” he said.
The update follows other questions from MPs this week over spending on state projects, including assets bought from SGS that remain unregistered.
FAQ
How long is the Malaba-Kampala railway?
The standard gauge line runs 272km from Malaba on the Kenyan border to Kampala, the minister said.
How much compensation has been paid for the Malaba-Kampala railway?
The government has paid Shs373.07bn to 7,721 of 12,946 project-affected people. Shs472.45bn is still outstanding.
Who is building the Malaba-Kampala railway?
Yapi Merkezi of Turkey holds the contract. It has completed preparatory works under a €75mn limited notice to proceed and is waiting for financial close before full construction.
When will construction start?
The minister gave no date. Full works depend on closing the financing and issuing a full Notice to Proceed.